Welton Farm Remedial Works

JML Contracts were contracted to carry out remedial works by excavating contaminated fill and placing Class D fill within the watercourse to protect the existing banking. The top of the 
Class D fill was topsoiled upon completion.

Close Asbestos monitoring was required while excavating with care to ensure minimum disruption and mitigating the spreading of asbestos particles.

Upon completion of the Class D installation, the client requested that JML installed Filter Units (Rockbags) due to their success on a previous contract which they had completed for Tayside Contracts.

  • Client: Tayside Contracts

Challenges

Close Asbestos monitoring was required while excavating with care to ensure minimum disruption and mitigating the spreading of asbestos particles.

SERVICES DELIVERED

Bulk excavation near watercourse, working in water, sediment control, contaminated soils, asbestos monitoring, working in watercourse with construction machinery to place Class D fill, topsoiling and planting.

Other Projects

If you would like to discuss your project, please get-in-touch.

To comply with data protection regulations (2018), we are unable to store and use your information unless you give us your permission. Please select Yes to allow this and rest assured we will never pass your details on to a 3rd party. View our data protection policy for details.*

If you would like to discuss your project, please

GET IN TOUCH